Construction of a complementary transfer system for MPWiK Warsaw

Informacje o realizacji


completed
Investment value
58 000 000 PLN
place
Warszawa
Area of activity
Water and wastewater
Service
Project execution management and investment supervision

Services consisting in the supervision of works related to the implementation of the project “Construction of a Complementary Transmission System – construction of a network and facilities connecting the drilled pipelines with the ”Świderska“ Plant and the ‘Farysa’ Plant, both in the design and execution stages of Phase 2.”

Construction of a complementary transfer system for MPWiK Warsaw

Supervision and technical, energy, legal, financial and accounting consulting, including legal services for the Client (MPWiK S.A.) during the implementation of the Project entitled “Construction of a Complementary Transmission System – building a network and facilities connecting the completed drilled pipelines with the ”Świderska“ and ‘Farysa’ plants, both in the design and execution stages of Phase 2”. The following services were provided:

  1. Management of the consulting service
  2. Client preparation and support during the design and construction period
  3. Providing consultancy and technical supervision and acting as the Client's representative
  4. Legal consulting
  5. Monitoring, financial and accounting consulting
  6. Reporting on the progress of works